Downtown Water Reliability Pipeline Replacement Project
Weekly update for the week of 2/23/26 (Phase 2)
This week crews will install new pipeline along Iowa Street crossing E. Mission Road Tuesday-Thursday.
The road will be restricted to one lane with flaggers between 7:30 a.m.-4:30 p.m.
Crews will then work up to E. Kalmia Street by Friday. (2-27-26)
Planned Shutdown scheduled for Thursday (2-26-26). Effected customers have recieved notifications
Base paving between Iowa Street and E. Mission Road is scheduled for Thursday (2/26/26)
Traffic control and road closures may be in place. Contractor will continue to maintain access for residence and businesses.
Project Description
The Fallbrook Public Utility District is in the construction phase for a large pipeline replacement project. With a projected cost of $4,050,000, the project will replace 9,000 feet of pipeline in the District’s service area in and near downtown Fallbrook. This portion of the FPUD water distribution system serves District residents, local small businesses, the Naval Weapons Station, and provides emergency service to Marine Corps Base Camp Pendleton. Many of the 80-year-old pipelines are approaching the end of their anticipated service life. The replacement is crucial to serve citizens and avoid environmental damage and threat to the community. Please see area map for the project below.